Reports Today
3
of 4 jobs reported
Open Blockers
2
need immediate action
PM Tasks Open
5
1 completed today
Scope Flags
2
pending review & pricing
Today's Field Reports3 submitted
View all โ
๐ฅ
Downtown Medical Center
Completed
Pulled wire floors 3โ4 east wing. Terminated 14 devices in Panel B. Corridor C detectors installed and tested.
Blocker
GC has not opened 3rd floor ceiling access โ crew blocked. Half-day delay risk by Thursday.
Materials
2 spools 14-2 FPLR wire + 6 FAPT-1 pull stations needed by EOD tomorrow.
Scope flag
Owner requested 4 additional lobby smoke detectors โ not on original drawings.
๐ข
Harbor View Office Tower
๐ฌ
Westside Retail Complex
Completed
Rough-in complete on zones 1 and 2. Zone 3 delayed โ inspector hasn't cleared the ceiling.
Blocker
Inspector clearance needed for zone 3 ceiling before any devices can go in. No ETA from GC.
Materials
Short 8 smoke bases โ not delivered with last order.
Airport Terminal B
No report submitted ยท Last: Yesterday ยท Mike Nelson
Open Blockers
2 activeDowntown Medical Center
GC has not opened 3rd floor ceiling access โ crew blocked. Half-day delay risk by Thursday.
Reported 3:42 PM
Westside Retail Complex
Inspector clearance needed for zone 3 ceiling before any devices can go in. No ETA from GC.
Reported 4:50 PM
PM Tasks
5 openContact GC re: 3rd floor ceiling access
Order 2 spools FPLR wire + 6 pull stations
Follow up on inspector clearance for zone 3
Reorder 8 missing smoke bases
Price out 4 lobby devices โ change-order to owner
Confirm Panel B sign-off with inspector
Scope Flags
2 to reviewDowntown Medical Center
Owner requested 4 additional smoke detectors in main lobby โ not on original drawings. Estimated 4โ6 hours additional labor.
Westside Retail Complex
GC asked crew to add 2 devices in storage room during walkthrough. Not scoped.
Materials Needed
3 items2 spools 14-2 FPLR wire
Downtown Medical
6ร FAPT-1 pull stations
Downtown Medical
8ร smoke detector bases
Westside Retail